How to Fix Delivery Delays Before It Ends Up in the PM’s Post-Mortem

By Glazix | June 6, 2025

No one plans for the driver to miss the access road. Or for the crew to idle two shifts waiting for a forklift. But the PM still has to explain it.

Delivery delays aren’t just a logistics issue—they’re a schedule risk multiplier. In refractory and industrial glass projects, where installs depend on precise cure times, preheat windows, and skilled labor scheduling, even a 6-hour delay can trigger cascading reschedules.

Common oversights that trigger delivery chaos:

Incomplete offload instructions

Misaligned dock hours or rigging plans

Driver unaware of site PPE or restricted access zones

By the time it shows up in the post-mortem, it’s too late. The project manager is already writing the delay justification—and chances are, you’re not getting the next order.

Distributors can fix this upstream:

GPS-tracked delivery ETAs sent to foremen

On-site delivery playbooks tied to project scope

Pre-shipment calls to field supervisors for readiness checks

This isn’t about being a trucking expert—it’s about being a timeline protection partner. The PM won’t remember that you were 20 minutes early—but they’ll never forget when you were four hours late without a call.