If You Can’t Get the Glass In, You Can’t Get the Job Done
For glass distributors, jobsite access is a scheduling variable that can make or break your install window. Cranes, boom lifts, freight elevators—all must be booked, aligned, and confirmed. If your access isn’t timed right, you miss your slot—and risk delay fees.
Coordinate Access with Crew Flow
Before shipping:
Confirm crane lift times
Validate swing-stage install zones
Ensure freight elevator availability
Understand where your material lands (loading dock, alley, roof edge)
Stagger Deliveries if Needed
If access is tight, split your delivery over two days. Don’t overload a staging area or block other trades. Use color-coded tags to track which glass goes where and when.
When Access is Pre-Coordinated, Everyone Wins
Installers move faster. The GC avoids bottlenecks. You reduce overtime. And most importantly, the glass gets installed with fewer touchpoints—reducing damage risk.